Salt Lake Winter Olympics 2002

The success of the solution provided to SOCOG led on to the Winter Olympics in Salt Lake City.

Originally, we were commissioned to provide asset tracking for all Furniture, Fuxtures and equipment going into the Village, however once the system was up and running the scope of what could be achieved was soon realized and the job at hand grew dramtically.

By the end of the games we had provided services to the follwing areas;

Logistics Department: Reports and space plans of where each individual item was to be placed.

Material Planning & Procurement Department: Asset quantities to order

Telecommunications Department: Asset location reports and drawings including Telephone handsets, printers faxes and telephone lines configurations. Including detailed asset information eg individual telephone, fax modem numbers and associated dialing access (international, national, domestic)

Technology Department: Asset location reports and drawings for a ll computers and associated hardware

Village Allotment: Assignment and tracking of spaces allocated to all countries and Organising Committee Departments.

Ratecard: Tracking of hired equipment by country

 

The Village Venue itself was also unique. It was an existing Venue (part of the University of Utah) with university owned assets already existing in spaces, which were to be used for Olympics. We were required as part of the contract to the University to return all University owned assets back to their original location after the Olympics. This Site under went several transformations. Starting out as the University Campus it was transformed into an Olympic Village, 60 hours after the Olympic Closing Ceremony everything had to be reset for the needs and use as a Paralympic Village. Finally, closing of the Paralympic Village all spaces had to be reset again back to the original University Layout two (2) weeks later.

 

Below is a summary of the space and assets tracked, moved and captured:

  • Unit of measurement - square feet by space - assigned areas only countries (doesn't include common areas of operational areas)

3,206,369 sq ft

320,636 sq meters

  • Document Management of accurate and up-to-date drawings

1,313 drawings

  • All University Furniture Fixtures and Equipment (FF&E) palcement and quantities

21,988 assets

  • All Olympic and Paralympic FF&E palcement and quantities that were signed over to a country

51,090 assets

  • All Rate Card items in accordance to where a Country requested to be space planned

1,846 assets

  • All telecom phones, gaxes and printers. This encompassed the 30 different phones, phone lines, connection point combinations as well as all phone numbers assigned to those lines and phones

1,393 assets

  • All of the Information Systems computer combinations/imaging including the Games Time Management System as well as the Administration networks for the Village and the Village Gateway

449 assets

TOTAL Assets

76,766 assets